County Hall Equipment Compound

Notice details

Published
Category
works
Buyer region
South East

Public buyer and contract winner

awarded to

Award value£52,885

  1. Awarded
    Completed
  2. Start
    Completed
  3. End
    Completed

Work description

Construction of external compound works which includes excavation of hard surfaced areas and removal of gullys and installation of new kerbing and compound sub base in addition to internal works to complete formation of Switchgear Room as further specified within the Scope of Works and Drawings attached.

The term of the contract shall be 31st October 2022 until 31st December 2022.

The closing date for receipt of Quotes is 14:00Hrs on 12th October 2022.