# HS2 Curzon Street Station - Structural Steelwork

> Tender notice from UK public-sector procurement sources.

## Key facts

- Public buyer: [Mace Dragados](/buyers/mace-dragados/contract-awards)
- Tender value: £40,000,000
- Published: 11 July 2024
- Planned start: 5 January 2026
- Planned end: 28 August 2029
- Stage: open_tender
- Procurement category: works
- Notice ID: c74dfecf-5010-43fd-b7c4-c480eed13e3a-766483
- OCID: ocds-b5fd17-ea70a4da-3e6b-4d3c-b10f-1603b4b8d420

## Description

Mace Dragados are seeking expressions of interest from the supply chain to deliver the logistics package\. The works comprise Design, supply, fabrication and erection of structural steelworks at the new Curzon Street Station works as follows Structural Steelwork \(roof, concourse, &amp; canopies\) incl Fire protection 1\. Concourse Framework - Framed members: Beams, columns, Trusses, permanent erecting, fittings, base plates and holding down bolts, blast cleaning, protective coatings, intumescent coatings \(120min\) connections 2\. Viaduct and Platforms - Framed members: Beams, columns, Trusses, permanent erecting, fittings, base plates and holding down bolts, blast cleaning, protective coatings, intumescent coatings \(120min\) connections 3\. Northern &amp; Southern retail units - Framed members: Beams, columns, permanent erecting, fittings, base plates and holding down bolts, blast cleaning, protective coatings, intumescent coatings \(120min\) connections 4\. Buttress Column steel work 5\. Main Roof - Framed members: Primary grid and secondary grid members, edge cantilevers, edge trusses, mullions, Beams, permanent erecting, fittings, steel cable, primary grid splicing, connections, blast cleaning, protective coatings, connections 6\. Platform canopies - Framed members: Beams, permanent erecting, fittings, base plates and holding down bolts, blast cleaning, galvanising, painting 7\. Other items - Weathering steel grade, metal decking, Edge protections, floor plates, holding down assemblies, end-cast plates, shear studs, roof temp works, PCC slabs, secondary steelwork A-CBSS-2840-S01 Other Scope: Roof Slide Works \(already designed by Specialist\) Class 3 Execution required, SSCS and BCSA/UKAS Accredited Additional information: "Estimated Contract Start Date" listed below is the actual start on site date

## Related contract awards

- [Specialist Tier 2 Subcontractor - Ground Source Heat Pumps](/contracts/ocds-b5fd17-1bbffb3b-ad0b-4938-b034-25a7f0ad27f1): Mace Dragados
- [HS2 Euston Station - Site Wide Temporary Utiliies and MEP Package](/contracts/ocds-b5fd17-04b8b712-8435-403a-93a4-62fbedc5a26d): Mace Dragados
- [HS2 Euston Station - Security Package](/contracts/ocds-b5fd17-b5cfd5c5-06d9-4aab-b4be-5466ca287656): Mace Dragados

## Source

[View the original notice on Contracts Finder](https://www.contractsfinder.service.gov.uk/Notice/c74dfecf-5010-43fd-b7c4-c480eed13e3a-766483)