Skip to content

Contract award record

Enabling Works Package

Tender value £497,620

Notice details

Published
Category
works
Buyer region
South East

Public buyer and contract winner

awarded to

Contract winner

T&B (Contractors) Ltd

Award value£301,722

  1. Start
    Completed
  2. Awarded
    Completed
  3. End
    Completed

Work description

Program - Works to be carried out between 25 July 2022 and 20/01/23 [26 weeks]. It should be noted that the temporary/permanent deck element of the building project must be completed by 20 August 2022.

Location - Atrium and adjacent plant room areas at Milton College; Chaffron Way Campus Woughton Campus West, Leadenhall, MK6 5LP.

Works - to install a temporary [or permanent] crash deck floor above the second-floor gantry level of the atrium; to install a sacrificial waterproof deck on the floor and install guttering & storm water drainage; to form a new access to the plantrooms/floor; strip out redundant ventilation plant; new plant room works; removal of the atrium glazing; pigeon protection works.

Contract/procurement - Single stage contract traditional IFC JCT contract with contractor's design portion.

Tender period - 20 June 2022 - 15 July 2022

Consultant team - Client Representative/Project Manager - Project Management Solutions; Architect/Principal Designer - Devonshire Architects; Structural Consultant - SOLUTION CE; M&E Consultant - Panda CE; Approved Inspector - LEXICON

Tender packs are available from Craig Pullen (craig@cpconsulting.org.uk)

Site visits are available on 4th, 5th & 8th July - details are in the tender pack.

Additional information: Tender packs are available from Craig Pullen (craig@cpconsulting.org.uk)

Related awards

Source: Contracts Finder · Notice 5f7862e0-8bfd-4015-a8d6-72f602f89526-559533