# CLOSED BRANCH LINES MINOR WORKS - BHS/5 - Remove close growing and disruptive tree growth\. Kill root systems to prevent re growth\. Make good/stabilise loose masonry and copings all over\. Repair timber fencing where broken\.

> Contract award record from UK public-sector procurement sources.

## Key facts

- Public buyer: [National Highways](/buyers/national-highways/contract-awards)
- Contract winner: [AMCO Rail](/contract-winners/amco-rail/public-sector-contract-awards)
- Award value: £40,875
- Tender value: £40,875
- Award date: 28 February 2025
- Published: 11 March 2025
- Contract start: 3 March 2025
- Contract end: 14 March 2025
- Stage: awarded
- Procurement category: works
- Notice ID: 1372d380-d0dc-407b-a4e2-6414f275adeb-832903
- OCID: ocds-b5fd17-840561bd-7bda-4104-bc50-25c3f9399cf0

## Description

CLOSED BRANCH LINES MINOR WORKS - BHS/5 - Remove close growing and disruptive tree growth\. Kill root systems to prevent re growth\. Make good/stabilise loose masonry and copings all over\. Repair timber fencing where broken\.

## Related contract awards

- [PDF - Framework - A120 Horsley Cross - Parkeston Rbt Harwich Safety Impt](/contracts/ocds-b5fd17-17b0789c-c4e1-4d50-acd5-06e497aace8c): National Highways
- [PDF Framework - A27 Falmer Footbridge Headroom](/contracts/ocds-b5fd17-ac2eb537-ce78-41bb-8f91-d6d652725e96): National Highways
- [PDF Framework - RM1016 Holyport interchange](/contracts/ocds-b5fd17-c92e4616-bb2e-4533-8dce-53b55a72aa09): National Highways
- [CLOSED BRANCH LINES MINOR WORKS - HLW/61 - Carry out site investigations as per Jacob's attached specifications\.](/contracts/ocds-b5fd17-cb81f8a7-9c6d-4615-a4c3-f9ab1cfb3336): National Highways
- [CLOSED BRANCH LINES MINOR WORKS - BHS/11 - Remove vegetation and treat remaining stems/trunks to prevent re growth\. Rake out, pressure fill and point deep open joints to all parts\.](/contracts/ocds-b5fd17-bd3a72fd-6b31-470d-87f0-468c3acf1394): National Highways
- [Project: pro\_19758 - HRE - CLOSED BRANCH LINES MINOR WORKS - AVE/2 - Replace missing wing wall copings\. Repair approach fences\. General Masonry Brickwork Repairs throughout to fractures, spalling and loose elements\. Apply date tabs to fractures for future monitoring\.](/contracts/ocds-b5fd17-af4760be-c1d3-462b-add5-34a34fadc491): National Highways

## Source

[View the original notice on Contracts Finder](https://www.contractsfinder.service.gov.uk/Notice/1372d380-d0dc-407b-a4e2-6414f275adeb-832903)