Contract award record
New awardSharnberry Mine Water Treatment Scheme (MwTS) Design & Build - Phase One
Notice details
- Published
- Category
- services
- Buyer region
- East Midlands
- Source
- View official notice
Public buyer and contract winner
Public buyer
MINING REMEDIATION AUTHORITYContract winner
John Graham Construction Ltd, Trading as GRAHAMAward value£482,030
- AwardedCompleted
- StartCurrent phase
- EndUpcoming
Work description
The opportunity is for the delivery of works comprising the design, construction, commissioning and handover of an operational Pumped - Passive Mine Water Treatment Scheme treating water currently discharging from Sharnberry mine, west of Hamsterley, County Durham.
This further competition seeks to appoint a contractor for Phase One services only under NEC4 ECC with Option X22.
The Mining Remediation Authority reserves the right, but is under no obligation, to proceed to Phase Two and Three with the successful contractor.
Proceeding to Phase Two and Three and awarding Phase Two and Three is subject to satisfactory agreement of target cost, risk and scope and will be represented for approval by the appropriate signatories at that time.