## Key facts

- Public buyer: HOMES &amp; COMMUNITIES AGENCY
- Contract winner: Dyer and Butler
- Award value: £1,158,644
- Tender value: £1,300,000
- Award date: 17 March 2016
- Published: 18 November 2016
- Contract start: 1 April 2016
- Contract end: 30 September 2017
- Stage: awarded
- Procurement category: works
- Notice ID: caa314b4-af26-4c65-9cca-92ed59a10ca9-84589
- OCID: ocds-b5fd17-31e35260-adc9-11e6-9901-0019b9f3037b

## Description

The Plot 3 Infrastructure works around Temple Quay being approximately 3,000m2 of pavement construction, generally comprise of stone capping with tarmac sub-base, sand and block paving, and associated works will include the following components: • Earthworks • Extension of Friary to Meads Reach Bridge o This work would comprise the extension of Friary as a two carriageway road east of Isambard Walk to Meads Reach Bridge\. o As part of this work the footway to the north of Friary \(adjacent to the Plot 3 development site\) would be extended to 6 metres in width, as will the footway to the south \(adjacent to the station\) would be made 8\.5 metres in width and include the provision of 6 new benches and an avenue of 5 new trees\. o The Friary will terminate with the provision of a new flexible use open space • Flexible Open Space o Space for temporary use will also be provided between the extended Friary and the listed retaining wall \(outside of development area\) o The area will be finished with seating terraces, and a planted bank to tie into the existing levels forming an earth retaining structure\. o This area will also need to be made capable of accommodating the occasional vehicle turning\. • Opening Isambard Walk as a two-way vehicular street between Friary and Temple Back East o The existing pedestrianised Isambard Walk will be opened for two-way vehicle access to create a link between Temple Back East and Friary, and to tie in with the existing road of the private estate\. As part of this work a new footway will also be provided to the eastern side of the Isambard Walk new carriageway\. o Isambard Walk will act as a shared space, and so will be treated to reduce the potential dominance of vehicles and reduce vehicle speeds o The footway, trees, cycle parking and street furniture to the west of Isambard Walk and in The Square would remain as existing\. • Temple Back East o The existing turning head area on Temple Back East would be removed, to allow two way vehicular access to Isambard Walk o Two way vehicular access will be maintained to Rope Walk, with a left turn out of Rope Walk into Isambard Walk to be provided for o Existing crossing will be maintained across from The Square to the footway on Temple Back East

## Related contract awards

- [Senior Manager - HR Strategic Projects](/contracts/ocds-b5fd17-e232c02f-1929-4541-8e2e-d9ed13eddea1): Homes &amp; Communities Agency
- [Legal Services Framework](/contracts/ocds-b5fd17-8a6262c3-91f6-4510-9fa3-ba3a39c47241): Homes and Communities Agency
- [HCA - Mile Bank Road- Demolition and Remediation](/contracts/ocds-b5fd17-e594ac0c-5768-4a92-bf5e-adf2e4feea5a): Homes and Communities Agency
- [HRE - CLOSED BRANCH LINES MINOR WORKS - SID/18 - ICE HOUSE LANE - DEVEG / TREE REMOVAL / FENCING](/contracts/ocds-b5fd17-4d8e5529-cad0-4dc0-be6a-7f779619798e): National Highways
- [HRE - CLOSED BRANCH LINES MINOR WORKS - SAD/127 - KNOWLE ROCK - DEVEG / TREE REMOVAL / FENCING](/contracts/ocds-b5fd17-b55ac856-b02f-4b3e-a847-c9f634912cf1): National Highways
- [HRE - CLOSED BRANCH LINES MINOR WORKS - SID/13 - KNAPP LANE - DEVEG / TREE REMOVAL / FENCING](/contracts/ocds-b5fd17-a043a92d-945d-44ef-978b-2a8813ae05a1): National Highways

## Source

[View the original notice on Contracts Finder](https://www.contractsfinder.service.gov.uk/Notice/caa314b4-af26-4c65-9cca-92ed59a10ca9-84589)