Skip to content

Contract award record

T1024 - Seagliders Relocation to Building 54 - AWARD

Notice details

Published
Category
works
Buyer region
East of England

Public buyer and contract winner

awarded to

Contract winner

MJS Projects (March) Ltd

Award value£0

  1. Awarded
    Completed
  2. Start
    Completed
  3. End
    Completed

Work description

The School of Environmental Science has a facility within Building 5 on the UEA campus, which houses underwater autonomous vehicles. These vehicles, known as Seagliders, are stored, serviced, maintained and prepared for dispatch on missions throughout the world, where they collect data from the seas and oceans, which is transmitted back to the UEA.

Building 5 forms part of the UEA's long-term refurbishment project relating to the Lasdun Wall, and as such is required to be vacated, with all users being relocated elsewhere. This project is required in order to relocate the Seagliders team and all their equipment to a vacant portion of Building 54 (also known as the Biomass Building), which was formerly used to store woodchip.

Tender Documents Issued 5th May 2023

Tenders Returned 9th June 2023 (12 noon)

Tender Analysis and Authorisation to Appoint 30th June 2023

Contract Award and Mobilisation 14th July 2023

Start on Site 31st July 2023

Practical Completion 20th October 2023 (or Contractor's own programme if they do not consider this achievable)