Skip to content

Contract award record

RfQ for sheet piles to retain 440 metre long footpath

Tender value £50,000

Notice details

Published
Category
goods
Buyer region
South East

Public buyer and contract winner

awarded to

Contract winner

Maxx Shoring

Award value£64,704

  1. Awarded
    Completed
  2. Start
    Completed
  3. End
    Completed

Work description

Quotations are requested to supply sheet piling to enable retaining of a new footpath adjacent to the Fleet Pond reservoir

The footpath will be built in two phases. Phase 1 will be constructed between 08/11/21 and 17/12/21, and Phase 2 will be constructed between 01/01/22 and 19/03/22.

Please see the attachment for details of how to bid.

Related awards

Source: Contracts Finder · Notice cf6535d3-4323-43f1-a148-e86a536a95e9-570642